PROJECT DESIGN · OFF-GRID COMMUNITY
Solar, Battery and Diesel Microgrid Design for an Off-Grid Town
The town’s existing power schedule
The town’s existing power schedule relies on three 500 kVA diesel generators taking turns to supply electricity for about 18 hours a day. The highest load in the profile used for this design was 457 kW at 6 a.m. That early peak matters because the town needs power before the solar array can contribute much. The goal of the proposed microgrid is to extend service to 24 hours a day while keeping the existing generators available.
The proposal adds about 480 kWp of ground-mounted solar, 964 kWh of nominal battery storage and a separate 500 kW power conversion system (PCS). At the generator station, the operator needs a clear way to choose which source feeds the existing distribution network as sunlight and demand change.
From the existing power station to the solar field
At the generator station, trace the outgoing feeder on the existing single-line diagram. That gives the design team a starting point for the transfer switch and a route back to the new equipment. Walk the same route with the operator to find out how the generators take turns and which loads need special attention when the supply changes.
The proposed solar field uses 774 modules rated at 620 Wp each. During the site walk, mark the ground available for the array and the route between the rows and the equipment yard. Leave room for people to inspect the modules and mounting structures after construction. Where the proposed route crosses a road or work area, confirm how the installer will protect the cables and preserve access.
The cabinet yard needs space for five enclosures and the equipment used to unload and place them. A location near the connection point can simplify cable routing, provided there is enough room for cabinet doors, service work and access around the yard. The field and cabinet positions in the project illustrations show one possible arrangement. The site team would settle the layout after checking the terrain, existing buried services and delivery access.
What goes in the equipment yard
Four outdoor, liquid-cooled DC cabinets provide 241 kWh of nominal battery energy each. Each cabinet is paired with a 120 kW solar input stage using maximum power point tracking (MPPT). Four 125 kW PCS modules in a separate cabinet convert power from the four DC branches to a shared AC output.
On the proposed single-line diagram, the shared AC output goes through a 500 kVA isolation transformer to one input of an automatic transfer switch (ATS). The existing diesel supply comes into the other input, and the town’s loads are downstream of the switch. The energy management system (EMS) coordinates the power conversion modules and transfer control. Before ordering, the project team should check the controls and protection at the existing generator station and confirm the transfer sequence with the operator.
| Proposed supply | Quantity | Role on this site |
|---|---|---|
| 620 Wp solar modules | 774 | Approximately 480 kWp of ground-mounted solar |
| Ground mounting and PV accessories | 1 lot | Mounting structures and PV cabling for the array |
| 241 kWh liquid-cooled DC battery cabinets | 4 | 964 kWh nominal in total, with 120 kW of solar input per branch |
| PCS cabinet with isolation transformer and ATS | 1 | Four 125 kW modules, a 500 kVA isolation transformer and the transfer switch |
| Energy management system | 1 | Controller and monitoring platform for the proposed system |
The three diesel generators are existing site equipment. Their controls, fuel arrangements and connection to the new transfer switch should be reviewed as part of the retrofit.
How the operating plan changes over a day
In daylight. When the solar and battery side is supplying the town, the plan is to use solar generation for the load first. Surplus generation charges the batteries. On an overcast day, the batteries may enter the evening with less energy available, so the operator needs a plan for bringing the diesel supply back into service sooner.
After sunset. The batteries can supply the load through the PCS for part of the evening if there is enough energy available. The operating plan needs a reserve for the hours ahead. The team should agree on when to transfer the town supply to the diesel side, taking into account the expected load, battery state of charge and the time the generator needs to be ready.
Before the morning peak. Work back from the 6 a.m. load. If the batteries are likely to reach their reserve before then, allow enough time for the diesel supply to be ready. The transfer settings depend on the site’s controls and load profile. For more on how these sources can be combined, see KUNETIC’s solar, battery and diesel microgrid solutions.
What it takes to plan for 24-hour service
Two checks drive the sizing. First, can the solar and battery side serve the town’s demand at its busiest time? Compare the load during the morning peak with what the PCS and transformer can deliver under site conditions. Ask about power factor and loads that start together. The 500 kW PCS rating and the 500 kVA transformer rating are both relevant to that check.
Second, how much energy would the town need through the hours it now goes without scheduled supply? Start with load measurements and the duration of each gap. If parts of the town are switched off during that window, estimate what people and businesses would use once service is available. That demand may be missing from the current metered profile.
Then test the schedule against the usable battery energy after reserves and losses, the solar conditions in different seasons, and the availability of the diesel generators. If reducing fuel use is part of the project, log the generator hours, loads and fuel consumption under the current schedule. That gives the team a baseline for comparing operating plans.
Equipment scope and budget
Use the supply list to request an equipment quote, then ask the supplier to price freight separately. Before comparing offers, check who will prepare the ground, build the foundations, make feeder changes and commission the system. The condition of the existing switchgear and the generator controls can change what the installer needs to supply.
What to share for a site-specific proposal
Send the town’s load profile and outage schedule, the generator nameplates and control details, and a single-line diagram of the existing power station. A site plan showing the proposed solar field, cabinet access and route to the distribution point helps the team assess the installation. With that information, KUNETIC can review the equipment scope and develop a proposed operating schedule for your site.
Frequently asked questions
Can we keep the existing diesel generators?
Yes. This design keeps the existing generators and connects the diesel supply to one input of the transfer switch. For a similar site, share the generator ratings, duty classification and control details so the project team can confirm how the existing equipment would start, transfer and continue serving the load.
Why does the 6 a.m. peak matter?
It occurs before much solar power is likely to be available. The team needs to know how long that demand lasts and which loads contribute to it. Those details affect how much battery reserve to hold overnight and when to prepare the diesel supply.
How long can the batteries supply the town?
It depends on the load during the hours the batteries are called on, their starting state of charge and how much energy the operator holds in reserve. Use the actual load profile to estimate the duration for the planned operating schedule.
What is included in the equipment package, and how can we get a quote?
The proposed equipment covers the solar modules and mounting, battery cabinets, PCS, isolation transformer, transfer switch and EMS. Share the load profile and site connection details for a quote that identifies the equipment, delivery and local installation scope.