PROJECT DESIGN · TOGO
Togo Commercial EV Charging: An AC and DC Site Design
A charging plan for a working automotive site
The proposed automotive site needs charging spaces for vehicles waiting for work or collection. These spaces must leave the work bays clear. Short visits need their own approach and exit. The layout gives these two groups separate charging areas.
This proposed Togo commercial EV charging design combines two AC charging units with three DC units. A 20kWp solar array, two 241kWh battery cabinets and a separately specified PCS support the equipment plan.
Arrival times, expected stays and energy needed before departure guide the layout. For the owner, charging has to fit around ordinary work. Staff still need practical access to the building and work areas throughout the day.
Give AC and DC charging different places on the site
In this design, the two 22kW-rated AC units serve a longer-stay area near the building. Vehicles waiting for work or collection can use that time for charging, subject to their AC charging capability.
The DC area has two 120kW-rated units and one 160kW-rated unit. Drivers making shorter visits can enter and leave this area without passing through vehicles waiting beside the work bays. The vehicle and available power determine the charging speed.
The layout needs room for turning, doors opening and people walking between vehicles and the building. Check charger position and cable reach against the intended vehicles. Keep connected cables within the charging area and preserve the routes staff need during ordinary work.
Keep the battery and PCS area accessible
The proposed storage area sits apart from the charging positions. It contains two outdoor battery cabinets and a separate PCS, with an approach for inspection and maintenance. Keep the cabinets and PCS in one area with space for cable routes and service access. Customer parking positions can then remain available for vehicles.
Each cabinet provides 241kWh of nominal battery energy, giving 482kWh in total. The separate PCS handles power conversion. The proposed unit has a 500kW equipment rating. Its AC-side version and electrical interface need to match the site design.
The solar array consists of 32 modules rated at 625Wp each. The design places the modules on the building roof. Measured roof conditions, mounting requirements and cable routes determine the final placement.
Match charging requests to the power available
Before setting charging priorities, record the vehicles' arrival times, departure deadlines and energy needs. A vehicle staying for several hours may allow more scheduling flexibility than one expected to leave soon.
The incoming supply and other site loads define the electrical capacity available alongside the battery system. EV charging load management lets the EMS coordinate charging priorities within the agreed battery limits. A 500kW PCS rating alone cannot tell the operator how much power each connected vehicle will receive.
The 20kWp array contributes solar energy during the day. Plan the charging day around solar generation and usable stored energy. Include how the site will replenish the batteries. KUNETIC needs the intended charging hours and energy demand to discuss a workable service plan.
For the 120kW units, the base connector option is GB. Share vehicle models and inlet photographs so the supplied interfaces can be matched before ordering.
What the equipment package and budget cover
The equipment package covers the roof array, storage and power conversion, together with the two charging areas and their energy management:
| Equipment | Proposed configuration | Role at the site |
|---|---|---|
| Solar array and mounting | 32 × 625Wp; 20kWp, with matched supports | Daytime solar input |
| Battery storage | 2 × 241kWh outdoor cabinets; 482kWh nominal | Stored energy for the agreed operating plan |
| External PCS | 1 × 500kW-rated unit; site-matched electrical version | Power conversion |
| AC charging equipment | 2 × 22kW-rated dual-connector units | Longer-stay charging positions |
| DC charging equipment | 2 × 120kW plus 1 × 160kW-rated dual-connector units | Shorter-visit charging positions |
| Energy management and monitoring | EMS and agreed monitoring scope | Charging priorities and system oversight |
Allow an indicative equipment budget of US$110,000–140,000, FOB Shenzhen. The selected charging interfaces, PCS supply version and agreed equipment scope determine the final quotation.
Freight, import charges, local foundations, construction and installation are separate. External distribution, protection, voltage adaptation where required and grid-connection work need their own agreed scope. If the business needs operating software or payment services, agree their scope and recurring fees separately.
Our commercial charging installation guide explains the wider site and contractor scope.
Bring your vehicle and site brief to KUNETIC
Send a dimensioned plan and photographs of the entrance, working areas, parking positions, roof and proposed equipment space. Add vehicle models, connector details, arrival and departure times, and energy needed per visit.
Include details of the site's electrical infrastructure: the incoming supply, distribution equipment and other loads. KUNETIC and the local installer can use these details to discuss equipment choices, electrical integration and the charging plan.
Questions about the Togo charging design
Why combine AC and DC charging at one automotive site?
A vehicle parked for several hours can use an AC position while waiting for work or collection. DC positions suit visits needing more energy within a shorter window. Allocate each vehicle according to its charging capability and planned departure.
Can all five charging units run at full power together?
That requires a review of site supply, other loads, battery limits and the vehicles connected. The equipment ratings are a starting point for that review. Agree the available power, sharing between connectors and operating settings before offering a simultaneous charging service.
How do solar and storage support the charging day?
Solar contributes energy when generation is available. Storage can release energy within its operating limits. The daily plan needs to consider solar yield, usable stored energy, replenishment and charging demand together. The required service hours should be part of the brief.
Does the equipment budget include local installation and electrical adaptation?
The range covers the proposed equipment supply on a FOB Shenzhen basis. Local installation, civil works and external electrical integration are separate. Request itemized scopes, including any required voltage adaptation. You can then assess the equipment and local-work quotations together.